Cymmer Primary

 

The internal works undertaken at Cymmer Primary School comprised of extensive remodelling and refurbishment of the junior block, while external works have included complete new roof covering, repairs to the front elevation, new entrance and access to the school, and the upgrading the MUGA. 

The internal works included a change of layout (forming new classrooms, toilets and dining hall), a new commercial kitchen and re-decoration throughout.

The main works were completed in 2018/19 and the project also includes the demolition of an existing canteen block.